Construction is going ahead as planned with 55 percent of the structural concrete now complete.
The concrete structure is complete to the 26th floor of the main resort tower, with walls extending to the 29th floor. The construction team are constructing one floor per week. The tower has grown by 44 meters in the last 100 days. There are currently 9,100 construction team member’s onsite, and more than 100 concrete trucks in one place on the site per day.
Wynn Al Marjan will offer 1,542 rooms and well-appointed suites. So far the tower has completed 1,121 of the guest rooms or 73 percent of the total. The elevator and escalator installation also began this month. Wynn Resorts maintains its own full-service design and architectural team.
Al Marjan Island will offer twenty two restaurants, bars and lounges that range from high- energy social destinations to fine-dining. The island will also include a nightclub and beach club hosting world-renowned DJ’s. There will also be an extensive poolscape adjacent to the beach with swimming pools, wading pools, water features, private cabanas and tropical landscape covering 3.6 hectares.
The resort will also include a shopping promenade spanning 15,000 square metres. The shopping promenade will offer top luxury boutiques, a five star spa, and a salon. Wynn Al Marjan will offer 7,500 square meters meeting and events centre, along with a theatre, they will offer parties, events, and bespoke entertainment services.
Wynn Resorts is developing the project in partnership with Marjan and RAK Hospitality Holding. It is anticipated to be the first integrated gaming resort in the Middle East North Africa (MENA) region.