Aleph Hospitality’s VP of technical services, Nadir Celiloglu speaks to Priyanka Praveen about how mistakes surrounding hotel construction can be avoided

In an exclusive interview with Hotelier Middle East, Aleph Hospitality’s vice president of technical services, talks about the common pitfalls of hotel construction and how owners can avoid them.

  • What factors most commonly cause delays to hotel construction and fit outs?

There are 434 hotels in the total pipeline for the Middle East, according to the latest data from STR (as of October 2019). This equates to a total of 119,991 upcoming rooms in the region. In the UAE specifically, 52,810 rooms are in construction, which represents 30.1% of the market’s existing supply.

If you’re a hotel owner investing in one or more of these hotels, you need construction projects that are on-time and on-budget, and an operator ready to hit the market with a well-planned, pre-opening strategy. With such a massive pipeline for the region, it’s imperative that you’re ahead of the competition. Being delayed is simply not an option.

Unfortunately, we still see many incidences in which the basic principles for hotel construction are not followed, often causing otherwise avoidable mistakes and costly delays. Usually, this is because the right expertise and specialist consultants are not engaged early on in their projects. In our opinion, based on decades of experience in hotel development both in the Middle East and internationally, these consultants are not optional; they’re essential. Investing in these partners at the outset is what determines the fate of your hotel construction project.

 

  •  How can these mistakes be avoided?

So, let’s take it right back to the beginning. Who should an owner bring on board, and in which order? First of all, hire a hospitality consultant. They will advise on the entire development process, support you on feasibility to establish your hotel’s capacity, star rating etc., and help set a realistic initial budget. On the recommendations of your hospitality consultant, engage your architect, engineering consultant and project manager. The timely and successful completion of the project is heavily dependent on the project management. These partners should all be hired during the initial stage of any hotel construction project.

  • How can a management company support the hotel owner throughout the construction process?

Ideally, you also want to appoint your hotel Management Company or operator at this initial stage. It is possible to engage them during the second stage, but for reasons outlined below, the earlier, and the better.

The operator will give the hotel a positioning and identity in the competitive market, develop a projected P&L to demonstrate the hotel’s potential performance, and shape the property’s design and development accordingly. The operator may bring an international brand with specific standards or work directly with the owner to create a unique positioning for an independent hotel. Either way, the management company usually influences the design alongside the architect and engineers. At Aleph Hospitality, for example, we’ve worked with developers to optimise designs and space utilisation to maximise ROI, including increasing room counts and streamlining back of house operations.
We also advise on what may seem like much smaller design details that can have a critical impact later on. At our upcoming Best Western Plus Westlands hotel in Nairobi, Kenya, opening in December, we identified the need for an additional fire exit staircase and extra AC and ventilation. We assess developments in line with international norms, brand standards and regional requirements, ensuring compliance early on. There is always something that needs to be modified or a detail that can be improved upon, and our operational insight and advice is usually gratefully received and implemented by consultants.

  • What additional tips can you share with owners embarking on a hotel development project?

Internally, it’s essential to work with your project manager to coordinate all parties and manage your budget. An underestimated budget will cause disruptions in the construction process, potentially spark disputes among partners, and delay your project. These situations are risky as quality is brought into question and too often sacrifices are made, impacting the success of your hotel and, critically, its ultimate market value. Moving forward, other partners will also need to be engaged as the project progresses. These include an interior designer, IT consultant, MEP consultant, landscaping consultant, kitchen consultant, laundry consultant and finally, when everything is in place, your lead contractor. Only then will construction start, and only then, will you be in full control of the outcome.