Product specification, timely delivery and planning for delays are among the key challenges in today’s purchasing landscape, according to experts
Product specification
“The main challenge is the specification of the product. People have very specific views and although we have a huge range it’s not always what they want. The product range in the UK is far different to that in the Middle East so we’re finding very specific requirements, which means we have to go outside our normal range. This adds time to the overall process.”
Nisbets Export, export advisor, Simon Garrett.
Reactivity vs proactivity
“Scheduling is a huge problem for us as suppliers. There is a schedule for hotel projects, but for new properties furniture is the last thing on their mind. So you’re negotiating for six or seven months and suddenly a month before opening they say ‘come on guys lets sign the contract and get the furniture from you’. The problem in Dubai is that so many projects are delayed so reactivity in a project is common.”
Sun and Shades vice president sales director, Roland Corko.
Timely delivery
“There is always a time-frame given to a supplier and by this date you should deliver. There is a 5-10% up and down, which is acceptable but a project delay of more than 30 days is not acceptable. As far as Doha is concerned this is a challenge. There are issues with delivery due to the local authorities and the paper work required.”
W Doha, director of purchasing, Anis Dawood.
Planning for delays
“If the supplier doesn’t have storage, for example in Saudi Arabia, it takes time for things to be shipped so delivery can take longer than expected. Some buyers don’t know how long processes take when they are in the planning process for a new hotel. They think that things can be delivered just like that, but they can’t. Some purchasing managers just buy something and come back, but they should be a real planner.”
Coral International Al Khobar general manager, Abdul Karim Al Atiq.